Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 22-069-15-50 03-2J9204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-PLA-80-254.0/25.4 NONE Progress payment No. 001 Payment period ending: 02-22-22 HANSEN BROS ENTERPRISES PO BOX 1599 GRASS VALLEY CA 95945 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,100.00 3,100.00 2. a. Extra Work 417,624.96 417,624.96 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 420,724.96 420,724.96 5. Mobilization 6. Total Work Completed 420,724.96 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 410,724.96 410,724.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 410,724.96