Dept. of Trans. PROGRESS Serial No. Contract No. Dept. of Trans. PROGRESS Serial No. Contract No. 05-203-10-13 10-0K4804 05-207-12-57 03-2M0204 PROGRESS PAYMENT VOUCHER %complete: %time: PROGRESS PAYMENT VOUCHER %complete: %time: Location: 13% 20% Location: 13% 25% 10-CAL-4-R49.6/R53.8 Federal Project: 03-NEV-20-R17.4/46.1 Federal Project: 10-CAL-4-R54.8/R58.0 NONE NONE Progress payment No. 03 Payment period ending: 07-20-05 Progress payment No. 01 Payment period ending: 07-20-05 NORTHWEST PAVING CENTRAL STRIPING SERVICE INC 3489 LUYUNG DRIVE 8115 SECLUDED VALLEY DRIVE RANCHO CORDOVA CA 95742 REDDING CA 96001 Escrow No. 00000 Escrow No. 00000 Total Estimate This Estimate Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,450.00 28,450.00 1. Contract Itms Without Mobil. 112,934.50 107,534.50 2.a. Extra Work 2.a. Extra Work b. Adjustment Comp. b. Adjustment Comp. 3. Materials on Hand 3. Materials on Hand 4. Earned Subject to Retention 28,450.00 28,450.00 4. Earned Subject to Retention 112,934.50 107,534.50 5. Mobilization 35,025.00 35,025.00 5. Mobilization 6. Total Work Completed 147,959.50 6. Total Work Completed 28,450.00 7. Deductions -3,500.00 -350.00 7. Deductions -375.00 -375.00 8. a.Contract Retentions -2,845.00 -2,845.00 8. a.Contract Retentions -11,293.45 -10,753.45 b. Unsatisfactory Prog. b. Unsatisfactory Prog. c. Reduction after 95% Comp. c. Reduction after 95% Comp. 9. Total pay to Contractor 25,230.00 25,230.00 9. Total pay to Contractor 133,166.05 131,456.05 10. Reduction Amt to Escrow 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 25,230.00 12. Net Pymt. this Estimate 131,456.05