Dept. of Trans. PROGRESS Serial No. Contract No. 05-207-13-04 03-2M0904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 15% 45% 03-SAC-99-R32.1/36.8 Federal Project: NONE Progress payment No. 02 Payment period ending: 07-20-05 TEICHERT CONSTRUCTION P O BOX 15144 SACRAMENTO CA 95851 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 226,606.90 225,180.90 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 226,606.90 225,180.90 5. Mobilization 75,000.00 75,000.00 6. Total Work Completed 301,606.90 7. Deductions -2,000.00 -2,000.00 8. a.Contract Retentions -22,660.69 -22,518.09 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 276,946.21 275,662.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 275,662.81