Dept. of Trans. PROGRESS Serial No. Contract No. 07-234-14-20 03-2M1004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 100% 03-YUB-20-R1.9/6.6 Federal Project: NONE Progress payment No. 10 Payment period ending: 08-20-07 MARTIN GENERAL ENGINEERING INC 12485 QUICKSILVER DRIVE RANCHO CORDOVA CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,347,781.94 0.00 2.a. Extra Work 553,228.86 221,495.77 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,901,010.80 221,495.77 5. Mobilization 11,600.00 0.00 6. Total Work Completed 1,912,610.80 7. Deductions -2,000.00 0.00 8. a.Contract Retentions -95,050.54 -11,074.79 b. Unsatisfactory Prog. 0.00 44.55 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,815,560.26 210,465.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 210,465.53