Dept. of Trans. PROGRESS Serial No. Contract No. 09-167-13-28 03-2M2404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 48% 03-YOL-113-R5.0/21.3 Federal Project: NONE Progress payment No. 02 Payment period ending: 06-19-09 BLAISDELL CONSTRUCTION INC P O BOX 493459 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 108,650.90 91,778.40 2.a. Extra Work 11,184.64 11,184.64 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 119,835.54 102,963.04 5. Mobilization 15,000.00 3,750.00 6. Total Work Completed 134,835.54 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 134,835.54 106,713.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 106,713.04