Dept. of Trans. SEMI-FINAL Serial No. Contract No. 07-020-13-16 03-2M3504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-PLA-80-R56.1/R66.3 Federal Project: NONE Progress payment No. 04 Payment period ending: 09-28-06 MARTIN BROTHERS CONSTRUCTION 20 LIGHT SKY CT SACRAMENTO CA 95828 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,027,613.75 69,730.50 2.a. Extra Work b. Adjustment Comp. -15,003.80 -15,003.80 3. Materials on Hand 4. Earned Subject to Retention 1,012,609.95 54,726.70 5. Mobilization 6. Total Work Completed 1,012,609.95 7. Deductions -58,000.00 16,400.00 8. a.Contract Retentions -45,020.53 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 45,020.53 0.00 9. Total pay to Contractor 954,609.95 71,126.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 71,126.70