Dept. of Trans. FINAL Serial No. Contract No. 08-163-13-47 03-2M3804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-NEV-89-1.1/4.0 Federal Project: NONE Progress payment No. 07 Payment period ending: 11-09-06 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 894350760 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 619,296.36 0.00 2.a. Extra Work 17,882.83 0.00 b. Adjustment Comp. -2,936.04 0.00 3. Materials on Hand 4. Earned Subject to Retention 634,243.15 0.00 5. Mobilization 5,000.00 0.00 6. Total Work Completed 639,243.15 7. Deductions 0.00 8,000.00 8. a.Contract Retentions -28,095.53 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 28,095.53 0.00 9. Total pay to Contractor 639,243.15 8,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,000.00