Dept. of Trans. PROGRESS Serial No. Contract No. 06-206-13-34 03-2M4704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 70% 03-COL-20-31.3/32.1 Federal Project: NONE Progress payment No. 02 Payment period ending: 07-20-06 J R ALTMAN GENERAL ENGINEERING CONTRACTOR 1557 EUGENE COURT YUBA CITY CA 95993 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 93,062.00 74,332.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 93,062.00 74,332.50 5. Mobilization 6. Total Work Completed 93,062.00 7. Deductions 8. a.Contract Retentions -4,653.10 -2,780.15 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 88,408.90 71,552.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 71,552.35