Dept. of Trans. PROGRESS Serial No. Contract No. 06-297-17-52 03-2M5404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 77% 03-YOL-5-0.8/ .0 Federal Project: NONE Progress payment No. 02 Payment period ending: 10-20-06 CLAYBORN CONTRACTING GROUP INC 10556 COMBIE ROAD AUBURN CA 95602 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 220,501.10 152,957.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 220,501.10 152,957.00 5. Mobilization 6. Total Work Completed 220,501.10 7. Deductions 8. a.Contract Retentions -11,025.06 -6,407.34 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 209,476.04 146,549.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 146,549.66