Dept. of Trans. PROGRESS Serial No. Contract No. 07-267-19-28 03-2M5904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 20% 03-ED-50-73.0/74.0 Federal Project: NONE Progress payment No. 01 Payment period ending: 09-20-07 ABSL CONSTRUCTION 29334 PACIFIC STREET HAYWARD CA 94544 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 253,356.05 253,356.05 2.a. Extra Work 8,474.95 8,474.95 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 261,831.00 261,831.00 5. Mobilization 6. Total Work Completed 261,831.00 7. Deductions -150.00 -150.00 8. a.Contract Retentions -13,091.55 -13,091.55 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 248,589.45 248,589.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 248,589.45