Dept. of Trans. PROGRESS Serial No. Contract No. 09-295-14-50 03-2M6204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 94% 03-ED-50-75.0/80.4 Federal Project: NONE Progress payment No. 07 Payment period ending: 10-20-09 VALLEY SLURRY SEAL COMPANY P O BOX 981330 WEST SACRAMENTO CA 95798 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,451,264.37 103,428.14 2.a. Extra Work 129,202.50 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,580,466.87 103,428.14 5. Mobilization 20,000.00 0.00 6. Total Work Completed 1,600,466.87 7. Deductions -64,860.79 -10,000.00 8. a.Contract Retentions -79,023.34 -5,171.40 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,456,582.74 88,256.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 88,256.74