Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 08-214-14-13 03-2M8204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-PLA-80-32.3/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 07-17-08 R A NEMETZ CONSTRUCTION CO INC P O BOX 32 WILTON CA 95693 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 153,347.00 132,342.50 2.a. Extra Work 3,104.55 3,104.55 b. Adjustment Comp. -1,719.50 -1,719.50 3. Materials on Hand 4. Earned Subject to Retention 154,732.05 133,727.55 5. Mobilization 6. Total Work Completed 154,732.05 7. Deductions -20,000.00 -20,000.00 8. a.Contract Retentions -2,100.45 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 2,100.45 2,100.45 9. Total pay to Contractor 134,732.05 115,828.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 115,828.00