Dept. of Trans. SEMI-FINAL Serial No. Contract No. 08-336-18-07 03-2M8504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-ED-50-60.5/64.4 Federal Project: NONE Progress payment No. 04 Payment period ending: 10-11-08 GOODWIN CONSTRUCTION INC 460 N YOSEMITE AVE STE 4 OAKDALE CA 95361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 223,646.80 1,500.00 2.a. Extra Work 11,843.94 8,570.98 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 235,490.74 10,070.98 5. Mobilization 6. Total Work Completed 235,490.74 7. Deductions -2,000.00 0.00 8. a.Contract Retentions -4,851.55 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 4,851.55 0.00 9. Total pay to Contractor 233,490.74 10,070.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,070.98