Dept. of Trans. PROGRESS Serial No. Contract No. 09-328-13-23 03-2M9004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 1% 3% 03-SAC-50-L0.6/R3.0 Federal Project: NONE Progress payment No. 01 Payment period ending: 11-19-09 BAY LINE CUTTING AND CORING INC 1033 YERBA BUENA AVENUE OAKLAND CA 94608 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,597.40 12,597.40 2.a. Extra Work 5,560.00 5,560.00 b. Adjustment Comp. 3. Materials on Hand 31,049.87 31,049.87 4. Earned Subject to Retention 49,207.27 49,207.27 5. Mobilization 6. Total Work Completed 18,157.40 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 49,207.27 49,207.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 49,207.27