Dept. of Trans. PROGRESS Serial No. Contract No. 10-326-06-53 03-2M9004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 81% 03-SAC-50-L0.6/R3.0 Federal Project: NONE Progress payment No. 12 Payment period ending: 11-19-10 BAY LINE CUTTING AND CORING INC 1033 YERBA BUENA AVENUE OAKLAND CA 94608 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,625,669.61 -9,716.00 2.a. Extra Work 96,366.30 27,451.65 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,722,035.91 17,735.65 5. Mobilization 108,604.53 0.00 6. Total Work Completed 1,830,640.44 7. Deductions -17,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,813,640.44 7,735.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,735.65