Dept. of Trans. PROGRESS Serial No. Contract No. 26-197-08-36 03-2N7404 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 100% Location: Federal Project: 03-SAC-5-0.0/3.5 NONE Progress payment No. 001 Payment period ending: 07-20-26 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 336,777.79 336,777.79 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 336,777.79 336,777.79 5. Mobilization 6. Total Work Completed 336,777.79 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 336,777.79 336,777.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 336,777.79