Dept. of Trans. PROGRESS Serial No. Contract No. 00-236-13-39 03-314404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 97% 03-BUT-162-13.9/15.9 Federal Project: STP-P162(23) BRST-P162(23) AC-P162(23) Progress payment No. 39 Payment period ending: 08-18-00 KIEWIT PACIFIC CO 5000 MARSH DRIVE CONCORD CA 94520 Escrow No. 00945 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,243,709.39 139,614.60 2.a. Extra Work 444,378.59 32,957.15 b. Adjustment Comp. -1,661.57 0.00 3. Materials on Hand 4. Earned Subject to Retention 9,686,426.41 172,571.75 5. Mobilization 1,039,460.00 0.00 6. Total Work Completed 10,725,886.41 7. Deductions -8,168.99 646.20 8. a.Contract Retentions -484,321.32 -8,628.59 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,233,396.10 164,589.36 10. Reduction Amt to Escrow 11. Payment to Escrow 484,320.00 12. Net Pymt. this Estimate 164,589.36