Dept. of Trans. PROGRESS Serial No. Contract No. 13-053-12-24 03-333824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 40% 31% 03-PLA-65-R15.0/R23.8 Federal Project: HPLU-6203(31) L-6203(31) Progress payment No. 07 Payment period ending: 02-20-13 DE SILVA GATES CONSTRUCTION LP P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,139,948.81 359,190.99 2.a. Extra Work 125,218.35 80,399.16 b. Adjustment Comp. -16,901.31 -135,926.01 3. Materials on Hand 4. Earned Subject to Retention 6,248,265.85 303,664.14 5. Mobilization 1,229,000.00 61,450.00 6. Total Work Completed 7,477,265.85 7. Deductions -13,000.00 7,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,464,265.85 372,114.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 372,114.14