Dept. of Trans. PROGRESS Serial No. Contract No. 13-168-15-44 03-333824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 53% 43% 03-PLA-65-R15.0/R23.8 Federal Project: HPLU-6203(31) L-6203(31) Progress payment No. 11 Payment period ending: 06-13-13 DE SILVA GATES CONSTRUCTION LP P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,992,182.49 691,607.00 2.a. Extra Work 286,308.04 107,813.00 b. Adjustment Comp. 403,243.44 -3,705.25 3. Materials on Hand 4. Earned Subject to Retention 8,681,733.97 795,714.75 5. Mobilization 1,229,000.00 0.00 6. Total Work Completed 9,910,733.97 7. Deductions -292,672.00 -282,672.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,618,061.97 513,042.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 513,042.75