Dept. of Trans. PROGRESS Serial No. Contract No. 13-294-14-40 03-333824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 62% 03-PLA-65-R15.0/R23.8 Federal Project: HPLU-6203(31) L-6203(31) Progress payment No. 15 Payment period ending: 10-17-13 DE SILVA GATES CONSTRUCTION LP P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,183,565.37 243,180.20 2.a. Extra Work 439,290.91 3,065.35 b. Adjustment Comp. 954,313.29 36,766.40 3. Materials on Hand 4. Earned Subject to Retention 12,577,169.57 283,011.95 5. Mobilization 1,229,000.00 0.00 6. Total Work Completed 13,806,169.57 7. Deductions -12,000.00 -7,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,794,169.57 276,011.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 276,011.95