Dept. of Trans. PROGRESS Serial No. Contract No. 14-204-10-59 03-333824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 86% 03-PLA-65-R15.0/R23.8 Federal Project: HPLU-6203(31) L-6203(31) Progress payment No. 25 Payment period ending: 07-17-14 DE SILVA GATES CONSTRUCTION LP P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,410,514.97 378,829.10 2.a. Extra Work 565,778.05 1,541.10 b. Adjustment Comp. 1,564,737.33 -6,760.50 3. Materials on Hand 4. Earned Subject to Retention 16,541,030.35 373,609.70 5. Mobilization 1,229,000.00 0.00 6. Total Work Completed 17,770,030.35 7. Deductions -5,000.00 5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,765,030.35 378,609.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 378,609.70