Dept. of Trans. PROGRESS Serial No. Contract No. 10-053-10-01 03-3338U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 35% 03-PLA-65-R12.2/R23.8 Federal Project: HPLU-6208(30) L-6208(30) DEMO Progress payment No. 21 Payment period ending: 02-22-10 DE SILVA GATES FCI A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND F C I CONSTRUCTORS INC P O BOX 2909 DUBLIN CA 94568Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 60,494,994.18 1,148,089.74 2.a. Extra Work 3,733,415.84 218,046.41 b. Adjustment Comp. 244,411.30 0.00 3. Materials on Hand 1,115,438.98 -149,461.88 4. Earned Subject to Retention 65,588,260.30 1,216,674.27 5. Mobilization 13,015,000.00 0.00 6. Total Work Completed 77,487,821.32 7. Deductions -48,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 78,555,260.30 1,216,674.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,216,674.27