Dept. of Trans. PROGRESS Serial No. Contract No. 11-207-10-06 03-3338U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 64% 03-PLA-65-R12.2/R23.8 Federal Project: HPLU-6208(30) L-6208(30) DEMO Progress payment No. 40 Payment period ending: 07-20-11 DE SILVA GATES FCI A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND F C I CONSTRUCTORS INC P O BOX 2909 DUBLIN CA 94568Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 101,793,448.30 2,106,003.08 2.a. Extra Work 10,057,685.77 51,491.43 b. Adjustment Comp. 548,252.94 51,339.75 3. Materials on Hand 350,569.89 -72,524.59 4. Earned Subject to Retention 112,749,956.90 2,136,309.67 5. Mobilization 13,700,000.00 0.00 6. Total Work Completed 126,099,387.01 7. Deductions -55,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 126,394,956.90 2,126,309.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,126,309.67