Dept. of Trans. PROGRESS Serial No. Contract No. 12-206-12-57 03-3338U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 83% 03-PLA-65-R12.2/R23.8 Federal Project: HPLU-6208(30) L-6208(30) DEMO Progress payment No. 52 Payment period ending: 07-19-12 DE SILVA GATES FCI A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND F C I CONSTRUCTORS INC P O BOX 2909 DUBLIN CA 94568Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 114,090,158.32 2,943,778.15 2.a. Extra Work 11,801,536.89 294,456.43 b. Adjustment Comp. 747,923.53 -48,431.16 3. Materials on Hand 131,400.00 -38,427.48 4. Earned Subject to Retention 126,771,018.74 3,151,375.94 5. Mobilization 13,700,000.00 0.00 6. Total Work Completed 140,339,618.74 7. Deductions -20,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 140,451,018.74 3,151,375.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,151,375.94