Dept. of Trans. PROGRESS Serial No. Contract No. 13-114-09-18 03-3338U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 93% 03-PLA-65-R12.2/R23.8 Federal Project: HPLU-6208(30) L-6208(30) DEMO Progress payment No. 61 Payment period ending: 04-18-13 DE SILVA GATES FCI A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND F C I CONSTRUCTORS INC P O BOX 2909 DUBLIN CA 94568Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 122,912,045.67 93,624.25 2.a. Extra Work 13,138,556.19 63,166.21 b. Adjustment Comp. 1,394,261.72 -1,872.55 3. Materials on Hand 4. Earned Subject to Retention 137,444,863.58 154,917.91 5. Mobilization 13,700,000.00 0.00 6. Total Work Completed 151,144,863.58 7. Deductions -23,273.98 -3,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 151,121,589.60 151,917.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 151,917.91