Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 05-152-12-02 03-338704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-BUT-99-T38.1/44.4 Federal Project: ACNH-P099(459) Progress payment No. 17 Payment period ending: 12-22-04 TULLIS AND HELLER INC P O BOX 493416 REDDING CA 96049 Escrow No. 02109 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,259,880.98 1,761.14 2.a. Extra Work 771,930.88 44,518.09 b. Adjustment Comp. 261,895.38 -62,693.11 3. Materials on Hand 4. Earned Subject to Retention 6,293,707.24 -16,413.88 5. Mobilization 231,564.00 0.00 6. Total Work Completed 6,525,271.24 7. Deductions -10,000.00 80,665.44 8. a.Contract Retentions -307,199.63 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 307,199.63 0.00 9. Total pay to Contractor 6,515,271.24 64,251.56 10. Reduction Amt to Escrow -307,190.00 0.00 11. Payment to Escrow 307,190.00 12. Net Pymt. this Estimate 64,251.56