Dept. of Trans. PROGRESS Serial No. Contract No. 03-085-07-57 03-3546U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 41% 03-SAC-80-9.1/17.9 Federal Project: ACNH-080-3(227) I-080-3(227) ACBH-080-3(227) Progress payment No. 09 Payment period ending: 03-20-03 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01961 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,338,113.32 952,126.87 2.a. Extra Work 78,301.67 20,980.20 b. Adjustment Comp. 59,973.00 59,973.00 3. Materials on Hand 217,608.84 217,608.84 4. Earned Subject to Retention 8,693,996.83 1,250,688.91 5. Mobilization 1,746,100.00 0.00 6. Total Work Completed 10,222,487.99 7. Deductions -14,994.00 0.00 8. a.Contract Retentions -607,942.34 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,817,160.49 1,250,688.91 10. Reduction Amt to Escrow 11. Payment to Escrow 607,940.00 12. Net Pymt. this Estimate 1,250,688.91