Dept. of Trans. PROGRESS Serial No. Contract No. 03-142-12-22 03-3546U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 38% 37% 03-SAC-80-9.1/17.9 Federal Project: ACNH-080-3(227) I-080-3(227) ACBH-080-3(227) Progress payment No. 11 Payment period ending: 05-20-03 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01961 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,323,674.99 843,983.94 2.a. Extra Work 381,666.50 99,019.40 b. Adjustment Comp. 59,973.00 0.00 3. Materials on Hand 189,934.85 0.00 4. Earned Subject to Retention 10,955,249.34 943,003.34 5. Mobilization 1,746,100.00 0.00 6. Total Work Completed 12,511,414.49 7. Deductions -19,351.80 -4,357.80 8. a.Contract Retentions -607,942.34 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,074,055.20 938,645.54 10. Reduction Amt to Escrow 11. Payment to Escrow 607,940.00 12. Net Pymt. this Estimate 938,645.54