Dept. of Trans. PROGRESS Serial No. Contract No. 04-328-17-14 03-3546U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 03-SAC-80-9.1/17.9 Federal Project: ACNH-080-3(227) I-080-3(227) ACBH-080-3(227) Progress payment No. 29 Payment period ending: 11-19-04 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01961 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,511,283.24 -80,348.55 2.a. Extra Work 1,291,264.21 97,876.56 b. Adjustment Comp. 1,425,715.79 -16,475.46 3. Materials on Hand 4. Earned Subject to Retention 30,228,263.24 1,052.55 5. Mobilization 1,838,000.00 0.00 6. Total Work Completed 32,066,263.24 7. Deductions -186,510.17 0.00 8. a.Contract Retentions -1,511,413.16 -52.63 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 30,368,339.91 999.92 10. Reduction Amt to Escrow 11. Payment to Escrow 1,511,360.00 12. Net Pymt. this Estimate 999.92