Dept. of Trans. SEMI-FINAL Serial No. Contract No. 06-137-13-19 03-3546U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SAC-80-9.1/17.9 Federal Project: ACNH-080-3(227) I-080-3(227) ACBH-080-3(227) Progress payment No. 33 Payment period ending: 05-17-05 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01961 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,590,915.57 0.00 2.a. Extra Work 1,849,432.23 48,606.23 b. Adjustment Comp. 1,702,499.70 -8,309.20 3. Materials on Hand 4. Earned Subject to Retention 31,142,847.50 40,297.03 5. Mobilization 1,838,000.00 0.00 6. Total Work Completed 32,980,847.50 7. Deductions -106,406.64 82,988.69 8. a.Contract Retentions -1,537,767.30 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 1,537,767.30 0.00 9. Total pay to Contractor 32,874,440.86 123,285.72 10. Reduction Amt to Escrow -1,537,760.00 0.00 11. Payment to Escrow 1,537,760.00 12. Net Pymt. this Estimate 123,285.72