Dept. of Trans. PROGRESS Serial No. Contract No. 08-111-13-38 03-3555U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 72% 03-ED-50-16.7/18.1 Federal Project: ACST-P050(110) PE-P050(110) BRLS-6203(14) Progress payment No. 25 Payment period ending: 04-18-08 MITCHELL ENGINEERING P O BOX 34367 SAN FRANCISCO CA 94134 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,703,895.62 1,070,658.47 2.a. Extra Work 539,090.09 495.81 b. Adjustment Comp. 367,936.56 0.00 3. Materials on Hand 448,624.63 -5,032.02 4. Earned Subject to Retention 19,059,546.90 1,066,122.26 5. Mobilization 3,500,000.00 0.00 6. Total Work Completed 22,110,922.27 7. Deductions -97,403.39 217,887.63 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 22,462,143.51 1,284,009.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,284,009.89