Dept. of Trans. PROGRESS Serial No. Contract No. 08-142-10-28 03-3555U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 63% 61% 03-ED-50-16.7/18.1 Federal Project: ACST-P050(110) PE-P050(110) BRLS-6203(14) Progress payment No. 26 Payment period ending: 05-20-08 MITCHELL ENGINEERING P O BOX 34367 SAN FRANCISCO CA 94134 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,091,785.18 387,889.56 2.a. Extra Work 553,452.27 14,362.18 b. Adjustment Comp. 263,062.85 -104,873.71 3. Materials on Hand 461,756.28 13,131.65 4. Earned Subject to Retention 19,370,056.58 310,509.68 5. Mobilization 3,500,000.00 0.00 6. Total Work Completed 22,408,300.30 7. Deductions -102,189.39 -4,786.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 22,767,867.19 305,723.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 305,723.68