Dept. of Trans. PROGRESS Serial No. Contract No. 08-330-08-38 03-3555U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 81% 82% 03-ED-50-16.7/18.1 Federal Project: ACST-P050(110) PE-P050(110) BRLS-6203(14) Progress payment No. 33 Payment period ending: 11-20-08 MITCHELL ENGINEERING P O BOX 34367 SAN FRANCISCO CA 94134 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,832,989.27 994,031.59 2.a. Extra Work 725,920.95 27,983.57 b. Adjustment Comp. 406,695.21 0.00 3. Materials on Hand 234,189.94 12,998.37 4. Earned Subject to Retention 26,199,795.37 1,035,013.53 5. Mobilization 3,500,000.00 0.00 6. Total Work Completed 29,465,605.43 7. Deductions -128,572.49 -67.30 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 29,571,222.88 1,034,946.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,034,946.23