Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 09-194-14-52 03-3555U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 97% 03-ED-50-16.7/18.1 Federal Project: ACST-P050(110) PE-P050(110) BRLS-6203(14) Progress payment No. 42 Payment period ending: 06-19-09 MITCHELL ENGINEERING P O BOX 34367 SAN FRANCISCO CA 94134 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,459,443.50 92,082.60 2.a. Extra Work 1,495,761.80 52,899.06 b. Adjustment Comp. 484,712.30 -4,982.00 3. Materials on Hand 151,806.67 0.30 4. Earned Subject to Retention 30,591,724.27 139,999.96 5. Mobilization 3,500,000.00 0.00 6. Total Work Completed 33,939,917.60 7. Deductions -149,372.14 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 33,942,352.13 139,999.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 139,999.96