Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 09-323-09-34 03-3555U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-ED-50-16.7/18.1 Federal Project: ACST-P050(110) PE-P050(110) BRLS-6203(14) Progress payment No. 46 Payment period ending: 09-28-09 MITCHELL ENGINEERING P O BOX 34367 SAN FRANCISCO CA 94134 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 29,456,039.11 436,447.72 2.a. Extra Work 1,683,792.26 74,277.01 b. Adjustment Comp. 495,079.64 -17,078.66 3. Materials on Hand 4. Earned Subject to Retention 31,634,911.01 493,646.07 5. Mobilization 3,500,000.00 0.00 6. Total Work Completed 35,134,911.01 7. Deductions -197,528.08 -22,786.94 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 34,937,382.93 470,859.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 470,859.13