Dept. of Trans. PROGRESS Serial No. Contract No. 10-144-13-30 03-366904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 7% 6% 03-BUT-99-8.6/13.2 Federal Project: SARR-P099(519) A-P099(519) Progress payment No. 03 Payment period ending: 05-20-10 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 182,246.05 177,246.05 2.a. Extra Work 21,073.70 21,073.70 b. Adjustment Comp. 16,265.62 16,265.62 3. Materials on Hand 136,745.84 -136,745.84 4. Earned Subject to Retention 356,331.21 77,839.53 5. Mobilization 296,400.00 296,400.00 6. Total Work Completed 515,985.37 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 647,731.21 369,239.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 369,239.53