Dept. of Trans. FINAL Serial No. Contract No. 09-061-09-09 03-367814 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-PLA-80-0.0/2.0 Federal Project: NCII-6203(16) PLN-6203(16) Progress payment No. 19 Payment period ending: 08-26-08 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,249,242.59 0.00 2.a. Extra Work 178,443.16 0.00 b. Adjustment Comp. 409,226.86 -1,655.40 3. Materials on Hand 4. Earned Subject to Retention 4,836,912.61 -1,655.40 5. Mobilization 335,400.00 0.00 6. Total Work Completed 5,172,312.61 7. Deductions -9,428.55 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,162,884.06 8,344.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,344.60