Dept. of Trans. PROGRESS Serial No. Contract No. 09-202-13-59 03-367824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 31% 16% 03-PLA-80-0.0/5.1 Federal Project: NCII-6203(24) PLN-6203(24) HPLU-6203(25) Progress payment No. 12 Payment period ending: 07-20-09 TEICHERT CONSTRUCTION P O BOX 15144 SACRAMENTO CA 95851 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,996,985.94 1,422,806.28 2.a. Extra Work 413,582.81 133,851.42 b. Adjustment Comp. 40,763.18 10,015.72 3. Materials on Hand 79,730.37 -15,920.23 4. Earned Subject to Retention 7,531,062.30 1,550,753.19 5. Mobilization 1,425,000.00 0.00 6. Total Work Completed 8,876,331.93 7. Deductions -10,000.00 4,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,946,062.30 1,554,753.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,554,753.19