Dept. of Trans. PROGRESS Serial No. Contract No. 09-236-14-37 03-367824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 20% 03-PLA-80-0.0/5.1 Federal Project: NCII-6203(24) PLN-6203(24) HPLU-6203(25) Progress payment No. 13 Payment period ending: 08-20-09 TEICHERT CONSTRUCTION P O BOX 15144 SACRAMENTO CA 95851 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,717,459.74 1,720,473.80 2.a. Extra Work 422,419.26 8,836.45 b. Adjustment Comp. 5,701.81 -35,061.37 3. Materials on Hand 24,634.23 -55,096.14 4. Earned Subject to Retention 9,170,215.04 1,639,152.74 5. Mobilization 1,425,000.00 0.00 6. Total Work Completed 10,570,580.81 7. Deductions -30,000.00 -20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,565,215.04 1,619,152.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,619,152.74