Dept. of Trans. PROGRESS Serial No. Contract No. 10-145-14-58 03-367824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 34% 03-PLA-80-0.0/5.1 Federal Project: NCII-6203(24) PLN-6203(24) HPLU-6203(25) Progress payment No. 22 Payment period ending: 05-20-10 TEICHERT CONSTRUCTION P O BOX 15144 SACRAMENTO CA 95851 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,771,693.04 653,003.60 2.a. Extra Work 1,050,764.33 21,104.75 b. Adjustment Comp. 171,858.43 -17,482.10 3. Materials on Hand 501,737.03 -53,061.09 4. Earned Subject to Retention 17,496,052.83 603,565.16 5. Mobilization 1,500,000.00 0.00 6. Total Work Completed 18,494,315.80 7. Deductions -40,000.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,956,052.83 613,565.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 613,565.16