Dept. of Trans. PROGRESS Serial No. Contract No. 11-168-08-30 03-367824 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 55% 03-PLA-80-0.0/5.1 Federal Project: NCII-6203(24) PLN-6203(24) HPLU-6203(25) Progress payment No. 36 Payment period ending: 06-16-11 TEICHERT CONSTRUCTION P O BOX 15144 SACRAMENTO CA 95851 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,315,399.63 6,308.00 2.a. Extra Work 1,484,956.24 3,862.27 b. Adjustment Comp. 371,680.35 15,686.95 3. Materials on Hand 34,204.44 0.30 4. Earned Subject to Retention 23,206,240.66 25,857.52 5. Mobilization 1,500,000.00 0.00 6. Total Work Completed 24,672,036.22 7. Deductions -21,600.00 -2,600.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 24,684,640.66 23,257.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,257.52