Dept. of Trans. PROGRESS Serial No. Contract No. 01-057-09-17 03-3696U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 03-SAC-50-16.1/17.3 Federal Project: ACHP-811(1) ACNH-P050(101) HP21-5288(7) Progress payment No. 19 Payment period ending: 02-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01304 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,391,313.56 4,800.00 2.a. Extra Work 1,021,133.23 1,131.92 b. Adjustment Comp. 163,950.85 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,576,397.64 5,931.92 5. Mobilization 700,000.00 0.00 6. Total Work Completed 7,276,397.64 7. Deductions -20,000.00 0.00 8. a.Contract Retentions -328,819.88 -296.59 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,927,577.76 5,635.33 10. Reduction Amt to Escrow 11. Payment to Escrow 250,000.00 12. Net Pymt. this Estimate 5,635.33