Dept. of Trans. PROGRESS Serial No. Contract No. 04-295-13-44 12-037104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 12-ORA-5-6.6/7.3 Federal Project: ACIM-005-2(888) STP-P001(446) AC-POO1(446) Progress payment No. 41 Payment period ending: 10-20-04 MARINA LANDSCAPE INC 1100 E KATELLA AVENUE ANAHEIM CA 928056621 Escrow No. 01624 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,073,905.75 1,580.00 2.a. Extra Work 45,132.75 0.00 b. Adjustment Comp. -12,363.41 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,106,675.09 1,580.00 5. Mobilization 29,705.00 0.00 6. Total Work Completed 2,136,380.09 7. Deductions 8. a.Contract Retentions -105,333.75 -79.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,031,046.34 1,501.00 10. Reduction Amt to Escrow 11. Payment to Escrow 105,250.00 12. Net Pymt. this Estimate 1,501.00 Dept. of Trans. PROGRESS Serial No. Contract No. 04-299-08-30 03-375604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 45% 52% 03-PLA-80-1.4/2.6 Federal Project: ACIM-080-3(230) Progress payment No. 10 Payment period ending: 10-20-04 R AND L BROSAMER INC P O BOX 238 ALAMO CA 94507 Escrow No. 02165 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,188,183.24 1,273,953.25 2.a. Extra Work 62,157.71 5,656.16 b. Adjustment Comp. 3. Materials on Hand 0.00 -4,189.23 4. Earned Subject to Retention 8,250,340.95 1,275,420.18 5. Mobilization 2,090,000.00 0.00 6. Total Work Completed 10,340,340.95 7. Deductions -358,488.31 -315,488.31 8. a.Contract Retentions -412,517.05 -1,792.19 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,569,335.59 958,139.68 10. Reduction Amt to Escrow 11. Payment to Escrow 412,510.00 12. Net Pymt. this Estimate 958,139.68