Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-167-09-02 03-375604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-PLA-80-1.4/2.6 Federal Project: ACIM-080-3(230) Progress payment No. 30 Payment period ending: 03-20-06 R AND L BROSAMER INC P O BOX 238 ALAMO CA 94507 Escrow No. 02165 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,731,416.51 117,440.00 2.a. Extra Work 1,519,184.99 219,125.83 b. Adjustment Comp. 479,044.04 -33,193.83 3. Materials on Hand 4. Earned Subject to Retention 22,729,645.54 303,372.00 5. Mobilization 2,200,000.00 0.00 6. Total Work Completed 24,929,645.54 7. Deductions -54,000.00 10,000.00 8. a.Contract Retentions -1,107,242.90 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 1,107,242.90 0.00 9. Total pay to Contractor 24,875,645.54 313,372.00 10. Reduction Amt to Escrow -1,107,240.00 0.00 11. Payment to Escrow 1,107,240.00 12. Net Pymt. this Estimate 313,372.00