Dept. of Trans. SEMI-FINAL Serial No. Contract No. 07-103-13-40 03-375604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-PLA-80-1.4/2.6 Federal Project: ACIM-080-3(230) Progress payment No. 34 Payment period ending: 03-20-06 R AND L BROSAMER INC 1777 OAKLAND BLVD., STE 300 WALNUT CREEK, CA 94596 Escrow No. 02165 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,809,920.62 0.00 2.a. Extra Work 1,796,858.64 58,352.13 b. Adjustment Comp. 532,377.39 15,783.20 3. Materials on Hand 4. Earned Subject to Retention 23,139,156.65 74,135.33 5. Mobilization 2,200,000.00 0.00 6. Total Work Completed 25,339,156.65 7. Deductions 8. a.Contract Retentions -1,107,242.90 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 1,107,242.90 0.00 9. Total pay to Contractor 25,339,156.65 74,135.33 10. Reduction Amt to Escrow -1,107,240.00 0.00 11. Payment to Escrow 1,107,240.00 12. Net Pymt. this Estimate 74,135.33