Dept. of Trans. PROGRESS Serial No. Contract No. 03-170-11-28 03-376104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 2% 16% 03-YUB-70-R0.4/R7.3 Federal Project: ACNH-P070-7(78) Progress payment No. 03 Payment period ending: 06-20-03 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02077 Total Estimate This Estimate 1. Contract Itms Without Mobil. 263,482.00 187,027.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 107,456.00 0.00 4. Earned Subject to Retention 370,938.00 187,027.00 5. Mobilization 6. Total Work Completed 263,482.00 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -37,093.80 -18,702.70 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 323,844.20 168,324.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 168,324.30