Dept. of Trans. PROGRESS Serial No. Contract No. 03-328-14-42 03-376104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 55% 55% 03-YUB-70-R0.4/R7.3 Federal Project: ACNH-P070-7(78) Progress payment No. 08 Payment period ending: 11-20-03 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02077 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,016,608.35 1,078,915.33 2.a. Extra Work b. Adjustment Comp. -250.00 -250.00 3. Materials on Hand 4. Earned Subject to Retention 7,016,358.35 1,078,665.33 5. Mobilization 1,258,750.00 0.00 6. Total Work Completed 8,275,108.35 7. Deductions -32,230.00 289,221.68 8. a.Contract Retentions -350,817.92 -53,933.27 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,892,060.43 1,313,953.74 10. Reduction Amt to Escrow 11. Payment to Escrow 350,810.00 12. Net Pymt. this Estimate 1,313,953.74