Dept. of Trans. PROGRESS Serial No. Contract No. 03-356-13-48 03-376104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 62% 03-YUB-70-R0.4/R7.3 Federal Project: ACNH-P070-7(78) Progress payment No. 09 Payment period ending: 12-19-03 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02077 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,465,632.35 449,024.00 2.a. Extra Work b. Adjustment Comp. -250.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,465,382.35 449,024.00 5. Mobilization 1,325,000.00 66,250.00 6. Total Work Completed 8,790,382.35 7. Deductions -32,230.00 0.00 8. a.Contract Retentions -373,269.12 -22,451.20 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,384,883.23 492,822.80 10. Reduction Amt to Escrow 11. Payment to Escrow 373,260.00 12. Net Pymt. this Estimate 492,822.80