Dept. of Trans. PROGRESS Serial No. Contract No. 04-021-16-09 03-376104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 68% 03-YUB-70-R0.4/R7.3 Federal Project: ACNH-P070-7(78) Progress payment No. 10 Payment period ending: 01-20-04 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02077 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,733,532.29 267,899.94 2.a. Extra Work b. Adjustment Comp. -250.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,733,282.29 267,899.94 5. Mobilization 1,325,000.00 0.00 6. Total Work Completed 9,058,282.29 7. Deductions -52,230.00 -20,000.00 8. a.Contract Retentions -386,664.11 -13,394.99 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,619,388.18 234,504.95 10. Reduction Amt to Escrow 11. Payment to Escrow 386,660.00 12. Net Pymt. this Estimate 234,504.95