Dept. of Trans. SEMI-FINAL Serial No. Contract No. 05-363-13-34 03-376104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-YUB-70-R0.4/R7.3 Federal Project: ACNH-P070-7(78) Progress payment No. 28 Payment period ending: 12-14-04 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 02077 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,744,296.26 0.00 2.a. Extra Work 397,903.31 0.00 b. Adjustment Comp. 648,245.03 255,540.87 3. Materials on Hand 4. Earned Subject to Retention 14,790,444.60 255,540.87 5. Mobilization 1,325,000.00 0.00 6. Total Work Completed 16,115,444.60 7. Deductions -5,630.00 60,000.00 8. a.Contract Retentions -678,556.65 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 678,556.65 0.00 9. Total pay to Contractor 16,109,814.60 315,540.87 10. Reduction Amt to Escrow -590,000.00 0.00 11. Payment to Escrow 590,000.00 12. Net Pymt. this Estimate 315,540.87